Construction Update-02/09/2026-02/20/2026

See update below to our early morning concrete pours (12am – 7am) for this week.

Please be advised dates and times are subject to change.

  • SOG North Side: Wednesday 02/18 @ 1am – 8-10 hour duration.

The below narrative outlines on-going and upcoming planned construction activities for the Westin project.

Our next update will be on 02/20/2026, please let us know if you have any questions.

Date Range:

  • 02/09/2026 – 02/20/2026

Construction Activities Occurring:

  • Trades working on forming and reinforcing SOG P9, SOG P10, SOG P11 and amenity area building foundations and roof slabs during normal working hours.
  • Precast parking garage erection and material staging/delivery.
  • Excavation for main pool.
  • Helical pile install for main pool.
  • MEP rough-in install continuing at south and north hotel elevated decks.
  • MEP underground rough-in install continuing at north hotel and convention area.
  • Elevator install ongoing.
  • North amenity canopy steel erection.
  • Metal decking install north hotel canopy.
  • CEP masonry install on-going. 
  • North hotel guestroom glazing install on-going.
  • South and North hotel interior light gauge framing interior and exterior on-going.
  • South and North hotel interior drywall install on-going.
  • We are tracking early morning concrete pour(s) (12am – 7am) as follows.  Please be advised dates and times are subject to change.
    • SOG P9 North Side: Wednesday 02/18/2026 @ 1am – 8-10 hour duration.
  • Waterproofing install around glazing openings on-going.
  • Deliveries:
    • Parking garage crane assembly, parking garage precast panels delivery and staging, concrete material and equipment trucking out, rebar, formwork, windows, various plumbing and electrical materials. 