See update below to our early morning concrete pours (12am – 7am) for this week.
Please be advised dates and times are subject to change.
- SOG North Side: Wednesday 02/18 @ 1am – 8-10 hour duration.
The below narrative outlines on-going and upcoming planned construction activities for the Westin project.
Our next update will be on 02/20/2026, please let us know if you have any questions.
Date Range:
- 02/09/2026 – 02/20/2026
Construction Activities Occurring:
- Trades working on forming and reinforcing SOG P9, SOG P10, SOG P11 and amenity area building foundations and roof slabs during normal working hours.
- Precast parking garage erection and material staging/delivery.
- Excavation for main pool.
- Helical pile install for main pool.
- MEP rough-in install continuing at south and north hotel elevated decks.
- MEP underground rough-in install continuing at north hotel and convention area.
- Elevator install ongoing.
- North amenity canopy steel erection.
- Metal decking install north hotel canopy.
- CEP masonry install on-going.
- North hotel guestroom glazing install on-going.
- South and North hotel interior light gauge framing interior and exterior on-going.
- South and North hotel interior drywall install on-going.
- We are tracking early morning concrete pour(s) (12am – 7am) as follows. Please be advised dates and times are subject to change.
- SOG P9 North Side: Wednesday 02/18/2026 @ 1am – 8-10 hour duration.
- Waterproofing install around glazing openings on-going.
- Deliveries:
- Parking garage crane assembly, parking garage precast panels delivery and staging, concrete material and equipment trucking out, rebar, formwork, windows, various plumbing and electrical materials.