Construction Update 1/26/26

The below narrative outlines on-going and upcoming planned construction activities for the Westin project.

Our next update will be on 02/06/2026, please let us know if you have any questions.

Date Range:

  • 01/26/2026 – 02/06/2026

Construction Activities Occurring:

  • Trades working on forming and reinforcing SOG P8, SOMD P4, surf pool interior slabs and amenity area building foundations during normal working hours.
  • Precast parking garage erection and material staging/delivery.
  • MEP rough-in install continuing at south and north hotel elevated decks.
  • MEP underground rough-in install continuing at north hotel.
  • Elevator install ongoing.
  • Steel detailing Convention Center normal working hours. 
  • North amenity canopy steel erection.
  • Metal decking install north hotel canopy.
  • CEP masonry install on-going. 
  • North hotel guestroom glazing install on-going.
  • South hotel interior light gauge framing interior and exterior on-going.
  • South hotel interior drywall install on-going.
  • We are tracking early morning concrete pour(s) (12am – 7am) as follows.  Please be advised dates and times are subject to change.
    • SOG P8 North Side: Tuesday 01/27/2026 @ 1am – 8-10 hour duration.
    • SOMD P4 North Side: Thursday 01/29/2026 @ 1am – 8-10 hour duration.
  • Waterproofing install around glazing openings on-going.
  • Deliveries:
    • Parking garage crane assembly, parking garage precast panels delivery and staging, concrete material and equipment trucking out, rebar, formwork, windows, various plumbing and electrical materials. 

Leave a Comment