Construction Update- Through May 1

Construction Update

The below narrative outlines on-going and upcoming planned construction activities for the Westin project.

Our next update will be on 05/01/2026, please let us know if you have any questions.

Date Range: 04/20/2026 – 05/01/2026

Construction Activities Occurring:

  • Trades working on forming and reinforcing SOG 13, SOG 14 and amenity area building foundations and roof slabs during normal working hours.
  • Precast parking garage washes, UG rough-in and caulking on-going.
  • Excavation for east spa, kiddie pool and north therapy spas.
  • MEP rough-in install continuing at south and north hotel elevated decks.
  • MEP underground rough-in install continuing at north hotel and convention area.
  • Elevator install ongoing.
  • North Convention Center roofing install.
  • Metal panels at roof screen wall install.
  • Convention center interior steel install.
  • Convention center masonry install on-going. 
  • L1 north hotel glazing install on-going.
  • Stucco install ongoing.
  • South and North hotel interior light gauge framing interior and exterior on-going.
  • South and North hotel interior drywall install on-going.
  • We are tracking early morning concrete pour(s) (12am – 7am) as follows.  Please be advised dates and times are subject to change.
    • SOG P13: Monday 04/20/2026 @ 1am – 6-8 hour duration.
    • SOG P14: Thursday 04/23/2026 @ 1am – 6-8 hour duration.
  • Waterproofing install around glazing openings on-going.
  • Deliveries:
    • Equipment trucking out, windows, various plumbing and electrical materials, parking garage precast panels.